August 8

August 9
August 16

We have demolished the 11th and 7th greens and are currently shaping the new greens.  Once the rough grading is complete we will install drainage lines, irrigation lines, signal wires, and sprinkler heads.  Once that is complete we will add the root zone mix to the greens surface, seed with the new hybrid bentgrass seed, and begin the grow in.  Sand will be added to the traps and the green surrounds will be covered with new sod.  We hope to have everything complete by the end of September. I will continue to post pictures here showing our progression.