Monday, March 25, 2013

March 2012
We have had a long snowy and cold winter and are anxiously waiting for the arrival of spring.  It is actually good that we have had constant snow cover to protect our turf from the bitter strong winds of winter.  Without the snow cover the cold winds dry out the turfgrass and root zone causing death through desiccation.

However, a Golf Course Superintendents greatest fear during the winter months is prolonged ice coverage.  While some ice formation is normal heavy rain events followed by extremely cold temperatures provide the greatest opportunity for

March 2013
 
winter damage.  Even though turf goes into dormancy during the winter it is still alive and needs oxygen, as well as expelling carbon dioxide.  Gas exchange is severely limited underneath thick ice coverage that persists for months on end.  Without proper gas exchange, the turfgrass may suffocate and die. 

I have been around to all of our greens recently and I have not found any ice build-up that would cause concern.  We will continue to monitor the situation and begin our push to have the new greens open on time.  All we need now is a little help from Mother Nature.



 

Monday, March 11, 2013

Retaining Walls

The retaining wall on the south end of the new cart bunker is almost complete.  The cap needs to be completed and then the back fill put in place and it will be done.  The retaining wall on the north end should be completed by weeks end.



Tuesday, February 12, 2013

The walls and roof of the new cart bunker are finished.  Next is the waterproofing, insulating and then back filling the east and south walls.


Back Right Of Back Tee Looking Down Fairway

Thursday, January 31, 2013

The west and north walls have been poured

We were fortunate to have a warm couple of days between the cold Arctic blasts allowing us to get the final 2 walls poured.  After the forms are stripped on Monday or Tuesday we will be ready to set the roof panels.


Monday, January 14, 2013

East & South Walls Poured

The footings were poured early last week and  Friday the south and east walls were poured.




Friday, January 4, 2013

Cart Bunker Update

The tee has been moved out of the way and the site is ready for the surveyor to come and stake out the building foot print. The surveyor is scheduled for Monday morning.




Thursday, January 3, 2013

Cart Bunker Started

We have started the excavation for the new cart bunker. They have moved approximately 75% of the old #1 tee and should be done moving the remainder by tomorrow afternoon.