Tuesday, May 7, 2013

Conveyor Moving Root Zone Mix


Conveyor moving 200 tons of root zone mix to the roof of the cart building.

Rooftop Tee

We have the soil on the rooftop of the cart bunker now and have graded it smooth. As soon as the rest of the grading is done surrounding the building we will be able to install the irrigation and complete the finish grade in preparation for the new sod. Once the sod is installed it will take at least four weeks to be rooted well enough to play from.




- Posted using BlogPress from my iPad

Thursday, May 2, 2013

Cart Bunker Update

The waterproofing has been completed, so today we installed the "root stop" fabric and most of the drainage system. On Monday the soil will be conveyed to the roof so we can start leveling in preparation to installing the new sod.




- Posted using BlogPress from my iPad