We were fortunate to have a warm couple of days between the cold Arctic blasts allowing us to get the final 2 walls poured. After the forms are stripped on Monday or Tuesday we will be ready to set the roof panels.
Thursday, January 31, 2013
Monday, January 14, 2013
Friday, January 4, 2013
Cart Bunker Update
The tee has been moved out of the way and the site is ready for the surveyor to come and stake out the building foot print. The surveyor is scheduled for Monday morning.
Thursday, January 3, 2013
Cart Bunker Started
We have started the excavation for the new cart bunker. They have moved approximately 75% of the old #1 tee and should be done moving the remainder by tomorrow afternoon.
- Posted using BlogPress from my iPad
- Posted using BlogPress from my iPad